8-Saturday Build Schedule

 

Priority 1

Priority 2

 March 1

Stand walls

Put up Porch Beams

25 volunteers

Brace, string, rebrace walls

 

 

Run Cap Plate

Blue Board or Felt Walls

 

Mark truss layout

 

 

Brick Flashing

 

 

Sheath walls

 

 

Load Trusses

March 8

Stand Trusses

Install Porch Posts

25 volunteers

Install K-Braces

Blue Board or Felt Walls

 

Install Z and X bracing

Rat runs/ Mid-Wed runs

 

Install Lookout ladders

Hurricane ties

 

Run Sub-Fascia

 

 

ADA blocking behind tub

Insulate behind Tub

 

Install Windows

 

 

Be deck ready

March 15

Deck roof/ Felt roof

Rat runs / Mid web runs

25 volunteers

 Fascia

Hurricane ties

 

Drip Edge

Blue Board or Felt Gables

 

Sheath Gables

ADA blocking / deadwood

 

Install Ext. Doors

Cut out thresholds

 

 

Attic access

 

Dried In

March 26

Run Shingles

Start Siding

25 volunteers

Start Ext. Trim:

Trim out Porch

 

Soffit

Brick Frieze

 

Siding Prep

 

 

 

 

 

Shingles 80% Complete

April 5

Finish Shingles

 

25 volunteers

Ridge Vent and Cap

 

 

Finish Soffit

 

 

Brick Frieze

 

 

 Siding

 

 

Siding Trim

 

 

Finish Roof

April 12

Finish Siding

 

25 volunteers

Finish Trim

 

day will likely end before 4 p.m.

Exterior Paint Prep

 

 

 

 

 

Be Paint Ready

April 19

Finish all Paint prep

rough grade lot by hand if necessary

25 volunteers

Finish all remaining trim

day will likely end before 4 p.m.

 

 

 

Paint house

 

2 coats of Paint Done

April 26

Smooth lot by hand if necessary

Finish Punch Items

25 volunteers

Lay sod

 

 

Plant trees

 

 

Plant shrubs, flowers

 

 

 

 

 

Exterior of house complete

 

 

 

 

two full weeks for inspections, punch out

 

 

 

 

 

 

May 10

Dedication

Move-in

 
 
   
 
 