| 8-Saturday Build Schedule
|
|
|
Priority 1 |
Priority 2 |
| March 1 |
Stand walls |
Put up Porch Beams |
| 25 volunteers |
Brace, string, rebrace walls |
|
| |
Run Cap Plate |
Blue Board or Felt Walls |
| |
Mark truss layout |
|
| |
Brick Flashing |
|
| |
Sheath walls |
|
| |
Load Trusses |
| March 8 |
Stand Trusses |
Install Porch Posts |
| 25 volunteers |
Install K-Braces |
Blue Board or Felt Walls |
| |
Install Z and X bracing |
Rat runs/ Mid-Wed runs |
| |
Install Lookout ladders |
Hurricane ties |
| |
Run Sub-Fascia |
|
| |
ADA blocking behind tub |
Insulate behind Tub |
| |
Install Windows |
|
| |
Be deck ready |
| March 15 |
Deck roof/ Felt roof |
Rat runs / Mid web runs |
| 25 volunteers |
Fascia |
Hurricane ties |
| |
Drip Edge |
Blue Board or Felt Gables |
| |
Sheath Gables |
ADA blocking / deadwood |
| |
Install Ext. Doors |
Cut out thresholds |
| |
|
Attic access |
| |
Dried In |
| March 26 |
Run Shingles |
Start Siding |
| 25 volunteers |
Start Ext. Trim: |
Trim out Porch |
| |
Soffit |
Brick Frieze |
| |
Siding Prep |
|
| |
|
|
| |
Shingles 80% Complete |
| April 5 |
Finish Shingles |
|
| 25 volunteers |
Ridge Vent and Cap |
|
| |
Finish Soffit |
|
| |
Brick Frieze |
|
| |
Siding |
|
| |
Siding Trim |
|
| |
Finish Roof |
| April 12 |
Finish Siding |
|
| 25 volunteers |
Finish Trim |
|
|
day will likely end before 4 p.m. |
Exterior Paint Prep |
|
| |
|
|
| |
Be Paint Ready |
| April 19 |
Finish all Paint prep |
rough grade lot by hand if necessary |
| 25 volunteers |
Finish all remaining trim |
|
day will likely end before 4 p.m. |
|
|
| |
Paint house |
| |
2 coats of Paint Done |
| April 26 |
Smooth lot by hand if necessary |
Finish Punch Items |
| 25 volunteers |
Lay sod |
|
| |
Plant trees |
|
| |
Plant shrubs, flowers |
|
| |
|
|
| |
Exterior of house complete |
| |
|
|
| |
two full weeks for inspections, punch out |
| |
|
|
| |
|
|
| May 10 |
Dedication |
Move-in |